On this page you will see the progress of the construction of our house and the rental accomodations. This page will be regularely updated.
Update 05 November: Almost done, next week the furniture.
Update 15 October 2008: We are finishing the rental houses and the swimming pool now. We are placing the tiles in the bathrooms and kitchens.
Update 27 September 2008: We had some slight problems but are on the move again. In the next few weeks the interior of our rental houses will be finished and we can start renting out. Expect new photos soon.
Update 16 August 2008: Almost finished, doors and windows have been placed, just needs finishing on the inside. The pool is halfway construction also.
Update 1 June 2008: The outside plastering is done and the window-sills are placed.
Update 25 May 2008: The outside of the rentals is nearly plastered.
Update 18 May 2008: The roof on the rental accomodations is done. Our house is plastered on the outside and partly on the inside.
Update 10 May 2008: The roof of our house is ready and they started making the roof on the rental accomodations.
Update 14 April 2008: The walls of the rental accomodations are up
Update 22 March 2008: We have the building license. The construction has started. The walls of our house are up allready and the foundation of the rental houses is ready.
|
|